Asbestos testing before renovation in BC: who must test, and when

Asbestos testing before renovation is required in BC: before work starts, the owner and the employers doing it must have a qualified person inspect the building for hazardous materials. The rule names no building age, and since January 1, 2024 the companies that survey for asbestos must hold a WorkSafeBC licence.

By the Delwin Construction team Updated

Open-concept white shaker kitchen with a quartz island, brass pulls and globe pendant lights

BC requires a hazardous materials inspection before renovation starts

Section 20.112 of BC’s Occupational Health and Safety Regulation sets the rule, in force since February 1, 2015. Before renovation or demolition work begins, every employer responsible for that work, and the owner, must make sure a qualified person inspects the building and the worksite for hazardous materials. The regulation’s list starts with asbestos-containing material and includes lead and other heavy metals.

Until those materials are safely contained or removed, no other work that may disturb them can go ahead. WorkSafeBC’s homeowner FAQ says the same in plain terms, and both the testing and the removal are licensed work in BC.

Before renovating in BC: the hazardous materials survey

  1. A qualified person inspects before work begins Section 20.112 puts the duty on the owner and on every employer responsible for the renovation or demolition.
  2. No building is too new for the rule The section sets no year of construction. WorkSafeBC's homeowner FAQ says many older homes contain some form of asbestos.
  3. Match the survey to the scope For a partial renovation, WorkSafeBC says only the areas being renovated need surveying. Before a whole-home demolition, every asbestos-containing material must be sampled and identified.
  4. Hire a licensed survey company WorkSafeBC lists asbestos surveyors among the businesses that need an asbestos abatement licence, mandatory since January 1, 2024, and publishes the licensed companies.
  5. Get the inspection report in writing It records where each sample came from, what each one is, the methods used, and the location and rough quantity of each hazardous material. WorkSafeBC expects 18 to 25 bulk samples from a typical home.
  6. Keep the report at the worksite The owner and the employers must make sure it is available on site while the work goes on.
  7. Notice of Project at least 48 hours ahead Moderate- and high-risk asbestos work needs this notice to WorkSafeBC, filed by the employers doing it and either the owner or the prime contractor.
  8. Wait for the written all-clear Work that may disturb the hazardous materials waits until a qualified person confirms in writing that they are safely contained or removed.
  9. Vancouver demolitions upload the reports The Hazardous Building Materials Assessment Report, plus a Post-Abatement Clearance Report if abatement was needed, goes on the permit before the demolition notification inspection.

Asbestos testing before renovation in BC: who must test, and when

Rules and permits, Older and heritage homes

Updated

By the Delwin Construction team

A licensed survey company does the testing

Since January 1, 2024, asbestos abatement contractors must be licensed to operate in BC, and their workers trained and certified. WorkSafeBC counts identifying suspect material and collecting samples as abatement work, so asbestos surveyors need the licence too. It publishes lists of licensed survey companies and abatement contractors, so check the name there before you sign, as you would when you check a contractor in BC.

A general contractor whose own workers do no asbestos work doesn’t need the licence; the survey company and the abatement contractor do. The regulation sets who is responsible for the inspection, not what a survey costs.

If the survey is the first step of a kitchen renovation or renovating an older house, book a free on-site consultation for the renovation itself.

The written report records what was found and where

The qualified person must put the inspection in a written report. Under section 20.112(3), it records where each sample came from, what each sample is and whether it is hazardous, and the methods used. It also locates each hazardous material, on drawings or plans if needed, with its approximate quantity. The report has to be available at the worksite while the work goes on.

WorkSafeBC’s homeowner FAQ (2023) adds its own expectations. It says a typical home survey should collect 18 to 25 bulk samples, and a report with fewer should explain why. It also says the report should carry the original lab results, not just a summary.

Notices and timing, from the survey to the all-clear

The inspection comes first, before the renovation or demolition work begins. If moderate- or high-risk asbestos work follows, WorkSafeBC must receive a Notice of Project at least 48 hours before that work starts on site. The employers doing it, and either the owner or the prime contractor, are responsible for the notice, and it includes the inspection report.

After the removal, a qualified person must confirm in writing that the hazardous materials are safely contained or removed. Renovation work that could disturb them waits for that confirmation.

A demolition in Vancouver adds the City’s step. Before the demolition notification inspection, the Hazardous Building Materials Assessment Report goes on the permit, with a Post-Abatement Clearance Report if abatement was required. If you’re weighing that path, see renovate or rebuild in Vancouver.

Starting without the survey breaks the regulation

Work that starts without the inspection is out of step with section 20.112, and the duty there names the owner as well as the employers. WorkSafeBC’s homeowner FAQ gives the practical reason: every material the work will disturb needs identifying first, or asbestos fibres may be spread through the home.

Local permits are a separate layer. The same FAQ notes that a local government may ask for a clearance letter from the survey company or the abatement contractor before it issues a permit.

Only the areas being renovated need surveying

For a partial renovation, WorkSafeBC says only the areas being renovated need to be surveyed. If the whole home will be demolished, every asbestos-containing material must be sampled and identified.

There is no exception for newer houses, because section 20.112 names no year. That covers houses built from 1965 to 1985, such as the Vancouver Special, as much as older ones.

The notice rule has one exception that matters here: the 48-hour Notice of Project isn’t required for the inspection work itself.

Questions people ask

What year do you have to test for asbestos in BC?

There's no cutoff year. Section 20.112 of BC's Occupational Health and Safety Regulation applies before the renovation or demolition of any building and names no date of construction. Newer houses need the inspection as much as old ones. WorkSafeBC tells homeowners to get the home tested before a renovation or demolition project starts.

Who can do an asbestos survey in BC?

A company with a WorkSafeBC asbestos abatement licence. Licensing became mandatory on January 1, 2024, and WorkSafeBC counts identifying suspect material and collecting samples as abatement work. It publishes the licensed survey companies, and its homeowner FAQ suggests asking whether the workers hold valid certificates and whether the lab that analyzes the samples is accredited.

Can you renovate a house with asbestos?

Yes, once the materials in the way are dealt with. Under section 20.112, renovation work that may disturb identified hazardous materials waits until they are safely contained or removed, and a qualified person confirms that in writing. Removal is licensed work in BC, and moderate- or high-risk asbestos work needs a Notice of Project to WorkSafeBC at least 48 hours before it starts.

Does a small renovation need a full asbestos survey?

Not of the whole house. WorkSafeBC's homeowner FAQ says that when only some areas will be renovated, only those areas need to be surveyed, though every material the work will disturb should be identified. The full-house survey, with every asbestos-containing material sampled and identified, is for a home that will be demolished.