Demolition permit in Vancouver: recycling rules, deposit and reports
A demolition permit in Vancouver for a house built before 1950 requires reusing or recycling at least 75% of its materials by weight, or 90% for a character house. You pay a $15,310 deposit when you apply, refunded if you meet those rates, and salvage and abatement can start only after the permit is issued.
By the Delwin Construction team Updated
Houses built before 1950 come down under recycling rules
Taking down a house in Vancouver needs a City permit: the City’s open data notes that building permits are required for demolitions. Under the Green Demolition By-law, a house built before 1950 must have at least 75% of its materials by weight reused or recycled. Hazardous materials are left out of the count. If the City deems the house a character house, the minimum rises to 90%.
The checklist below sorts the requirements by the age and status of the house. Outside the City of Vancouver, each municipality sets its own demolition rules.
What demolishing a Vancouver house requires, by the age of the house
- Any age: a hazardous materials inspection by a qualified person Under BC's workplace safety rules, the owner and the employers must arrange it before any demolition or salvage work begins.
- Any age: hazardous materials reports on the permit Before you ask for the demolition notification inspection, upload the Hazardous Building Materials Assessment Report. If abatement was needed, add the Post-Abatement Clearance Report.
- Any age: salvage and abatement only after the permit is issued The City says salvage of non-structural building parts and abatement work may begin only once the demolition permit has been issued.
- Built before 1950: reuse or recycle at least 75% by weight Hazardous materials are left out of the weight.
- A house the City deems a character house: 90% A character house is typically a detached house built before January 1, 1940 that meets the City's character merit criteria.
- Built before 1950: a $15,310 deposit with the application It's refunded if you meet the reuse and recycling requirements.
- Built before 1910, or on the Vancouver Heritage Register: salvage at least 3 tonnes of wood The minimum is 3 metric tonnes of salvaged wood.
- A buried oil tank, if there is one: its own removal permit The City's tank removal or abandonment permit costs $300 and is valid for 90 days, and tanks unused for two years must come out.
- Trees 20 cm or more across at 1.4 m: approval before they come down On a development site it comes with the development or building permit; otherwise it takes a tree removal permit.
The $15,310 deposit comes back if you reach the recycling rate
For a demolition permit with reuse and recycling requirements, the City asks for a $15,310 deposit when you apply. It refunds the deposit if you meet those requirements. The demolition permit fee itself isn’t in this guide, because we haven’t confirmed the current figure.
Before any demolition or salvage work begins, the owner has a duty of their own. Under BC’s Occupational Health and Safety Regulation, the owner and every employer responsible for the work must have a qualified person inspect for hazardous materials.
If you’re weighing renovating instead of rebuilding, book a free on-site consultation and get a renovation quote to set beside the demolition route.
Hazardous materials reports come before the City’s inspection
The qualified person collects samples, identifies the hazardous materials, such as asbestos or lead, and writes a report of where they are and roughly how much there is. Where materials have to be removed or contained, a qualified person then confirms in writing that it was done safely.
The City checks for those reports on the permit. Before you ask for the demolition notification inspection, upload the Hazardous Building Materials (HBM) Assessment Report. If abatement (removing or containing hazardous materials) was needed, add the Post-Abatement Clearance Report.
Asbestos abatement in BC is licensed work. Since January 1, 2024, abatement contractors must hold a licence from WorkSafeBC to operate.
Salvage and abatement wait for the permit
The steps of a Vancouver house demolition, in order. Step 1 can happen before you apply, and it must happen before any work starts.
- A qualified person inspects for hazardous materials and writes the report.
- You apply for the demolition permit, with the $15,310 deposit for a house built before 1950.
- The permit is issued. Only then may salvage of non-structural parts and abatement work begin.
- For moderate- or high-risk asbestos work, WorkSafeBC must receive a Notice of Project at least 48 hours before it starts. The employers doing the work and either the owner or the prime contractor make sure it goes in.
- You upload the HBM report, and the clearance report if abatement was needed, then request the demolition notification inspection.
- The deposit comes back once you’ve met the reuse and recycling requirements.
We haven’t confirmed how long the City takes to issue a demolition permit, so no wait is given here. A house on the Vancouver Heritage Register can take longer, as the last section explains.
Missing the rate or skipping the permit costs money
If the job falls short of the reuse and recycling requirements, the City keeps part or all of the $15,310 deposit, under Appendix C of the Green Demolition By-law.
Starting work that needs a permit before you have one brings in the City’s work-without-permit rules. All work stops while the permit is processed, and the penalty is typically double the original permit fee. WorkSafeBC’s rules add a hard stop: no demolition work that may disturb the hazardous materials found can go ahead until they’re safely contained or removed.
Heritage-listed, pre-1910 and First Shaughnessy houses have extra rules
A house built before 1910, or one listed on the Vancouver Heritage Register, must also yield at least 3 metric tonnes of salvaged wood. For a building on the Register, or one that may have heritage value, Council can delay the demolition, giving it temporary protection for up to 120 days.
In the First Shaughnessy Heritage Conservation Area, any demolition also needs a heritage alteration permit.
The 90% rate depends on whether the City deems the house a character house. For applications in R1-1 zoning, the City says it generally doesn’t ask for a character assessment at present, so the 75% rate applies.
If a bin, a delivery or a crane will sit on the street during the work, read our guide to street use permits in Vancouver. Trees on the lot follow the tree removal permit rules.
Questions people ask
Do I need a permit to demolish a house in Vancouver?
Yes. The City of Vancouver requires a permit for a demolition, and a house built before 1950 also carries reuse and recycling minimums backed by a $15,310 deposit. A qualified person has to inspect for hazardous materials before any demolition or salvage work, and salvage and abatement can't start until the permit is issued.
What is the green demolition deposit in Vancouver?
It's the $15,310 deposit the City of Vancouver requires when you apply for a demolition permit with reuse and recycling requirements, which apply to houses built before 1950. The City refunds it if you meet those requirements. If you don't, it keeps part or all of the deposit under Appendix C of the Green Demolition By-law.
What has to happen before a house is demolished in Vancouver?
A qualified person inspects the house and the site for hazardous materials and writes a report. Abatement, if needed, waits until the permit is issued, and a qualified person confirms in writing when it's done. Both reports go on the permit before you request the City's demolition notification inspection. On a pre-1950 house, the deposit is paid at application.
Sources
- City of Vancouver: Demolition permit with recycling and deconstruction requirements
- WorkSafeBC: OHS Regulation Part 20, Construction, Excavation and Demolition (s.20.112 Hazardous materials)
- City of Vancouver: Vancouver Heritage Register (VHR)
- City of Vancouver Open Data Portal: Issued building permits