Tenant improvement permit in Vancouver: which City path fits
A tenant improvement permit in Vancouver is the City building permit for a leased business space, needed when the work moves interior walls or plumbing, electrical or gas lines. Office tenants in buildings on the City's TIPs list can apply through a stream that aims to finish its first review in 5 to 10 business days.
By the Delwin Construction team Updated
Moving walls, plumbing, wiring or gas in a business space needs a City permit
The City of Vancouver’s permit rule for renovations turns on what the work moves: interior walls, or existing plumbing, electrical or gas lines. So a new layout in a leased office, shop or clinic needs one whenever it moves a wall, a sink, a circuit or a gas line. Building permit fees are set in the Vancouver Building By-law. A change in how a building is used falls under the Zoning and Development By-law.
The City runs more than one route to that permit. Its Tenant Improvement Program (TIPs) is a stream for office tenants. It also has a field review stream, and one City checklist sets the application requirements for field review and TIPs minor renovations. Bigger jobs can need a development permit first: the City names large projects, zoning relaxations and some types of land use.
The table sets the paths side by side. A space in Burnaby, Richmond or elsewhere outside the City of Vancouver needs that municipality’s permits instead.
| Who it fits | What to expect | |
|---|---|---|
| Tenant Improvement Program (TIPs) | Office tenants in a building on the City's TIPs list; office buildings with a building permit applied for after January 31, 2007 are on it automatically | Initial review: the City aims for 5 to 10 business days. The permit follows 1 to 2 business days after the field review inspection passes |
| Field review (minor renovation) | Smaller renovations; the City's minor renovation application checklist covers field review and TIPs together | Check the City's field review page to confirm your scope qualifies before you apply |
| Standard building permit | Commercial renovations outside both streams; large projects, relaxations and some land uses need a development permit first | The City reported a 32-day median for commercial renovation permits in July 2024, down from 56 days in 2022 |
| Switching between office, retail, health care office, salon or wellness centre uses | Up to 300 m² of floor space: no development permit for the change of use | A building permit still applies if the work moves walls or services, and an occupancy permit before you open in the new use |
| Restaurant, café or other food premises | Any construction or alteration of food premises | Vancouver Coastal Health must approve the floor plans before construction starts, on top of the City permits |
Your building sets the path, and the cost of work sets the fee
Whether TIPs is open to you turns on two things: an office tenancy and a building on the City’s TIPs list. Any commercial office building with a building permit applied for after January 31, 2007 is on the TIPs list automatically. In an older building, ask the City whether it’s listed before you plan around the TIPs timeline.
If the unit is in a strata building, check the common property first. Work that touches common or limited common property needs the strata corporation’s written approval before the City issues a building or trade permit.
The City’s 2026 fees come from its November 2025 council report on fee increases. The opening $5,000 of estimated cost is charged $217. From there to $50,000 the rate is $13.90 per $1,000, and above $50,000 it’s $7.04 per $1,000. A clinic adding sinks also needs a plumbing permit: $282 for one to three fixtures, then $88.70 for each extra one. Electrical and gas permits in Vancouver come from the City too, not from Technical Safety BC. For a full example, read City of Vancouver building permit fees.
If you’re planning a commercial renovation in Vancouver, settle the permit path while the layout can still change. To talk it through, book a free on-site consultation.
Under TIPs, the inspection comes before the permit
On the TIPs stream, the City starts with an initial review of the application. A building inspector then does a field review inspection of the space, and the permit is issued 1 to 2 business days after it passes. Have the space and the drawings ready for that visit. A reinspection made necessary by faulty, incomplete or not-ready work costs $282 at the City’s 2026 rates.
A change of use adds a check at the end. The City must issue an occupancy permit before you occupy commercial space after a change to its proposed use. Apply at least 3 weeks before your planned opening, once the permits for the work have been issued.
TIPs aims for days; standard commercial permits took a median of 32 days in 2024
Here is how the City’s published targets and figures line up:
- TIPs initial review: the City aims to finish it within 5 to 10 business days.
- TIPs permit: issued 1 to 2 business days after the field review inspection passes.
- Standard commercial renovation permit: a median of 32 days, as the City reported in July 2024, against 56 days in 2022.
- Occupancy permit after a change of use: apply at least 3 weeks before opening.
- Starting work: it must begin within 6 months of the permit’s issue date, or the permit becomes void.
The TIPs numbers are targets, and the 32 days is a 2024 median, so about half of those permits took longer. Build the gap into the lease start and the opening date.
Starting without a permit stops the work and typically doubles the fee
The City’s “When you need a permit” page spells out the cost of starting early. Unpermitted work has to stop until a permit is processed. The City typically charges a penalty of twice the original permit fee, and finished work may have to come out.
A change of use carries a second risk. The occupancy permit has to be issued before you occupy the space in its new use, so opening day depends on it.
Some changes of use skip the development permit; food premises need more
The Zoning and Development By-law names five uses a space of up to 300 m² can switch between without a development permit. They are general office, retail store, health care office, barber shop or beauty salon, and beauty and wellness centre. The renovation itself still follows the building permit rule above, and the occupancy permit still applies to the new use.
Food premises sit at the other end. In BC, nobody may build or alter food premises until a health officer has approved the plans and specifications. Vancouver Coastal Health reviews and approves the floor plans before construction begins, renovations included. For a café or restaurant fit-out, that approval runs alongside the City permits, not instead of them.
Questions people ask
How long does a tenant improvement permit take in Vancouver?
On the City's TIPs stream for office tenants, the City aims to finish its initial review in 5 to 10 business days. The permit follows 1 to 2 business days after the field review passes. Outside TIPs, the City reported a 32-day median for commercial renovation permits in July 2024. An issued permit lapses if work hasn't begun within 6 months.
Do I need a permit to renovate an office in Vancouver?
Yes, if the layout change moves a wall, a pipe, wiring or a gas line. Office buildings with a building permit applied for after January 31, 2007 are automatically on the City's TIPs list, and their tenants can apply through the TIPs stream. In an older building, ask the City whether it's listed, or look at the field review stream before a standard application.
Do I need a development permit to turn a shop into a salon in Vancouver?
Not if the space is 300 m² or smaller. Retail store and barber shop or beauty salon are both on the by-law's list of uses that can switch between each other without one, along with three others. A building permit still covers work that moves walls or services, and the City must issue an occupancy permit before you open as a salon.
Sources
- City of Vancouver: Tenant Improvement Program (TIPs)
- City of Vancouver: Field Review and Tenant Improvement Program (TIPS) Minor Renovation Building Permit Application Requirements
- City of Vancouver: Permitting Improvement Program progress backgrounder (2024)
- City of Vancouver: Zoning and Development By-law, Section 4 (development permit exemptions)
- City of Vancouver council report: 2026 Fee Increases for Rezoning, Development, Building, and Other Related Applications and Permits
- City of Vancouver: Get an occupancy permit
- Vancouver Coastal Health: Food Service Permits and Health Approvals