Commercial renovation permit times in Vancouver run from a 21-day median for offices to 38 days for beauty and wellness centres, in the year to 22 November 2026. A health care office sits at 31 days, but a lease has to absorb the slow tail: 1 in 10 of those permits took longer than 101 days.

By the Delwin Construction team Updated

Key findings: offices are the most common and the quickest

General Office is the largest group in the City of Vancouver’s open data on lower-complexity commercial renovation permits, and its permits come through in the fewest days. For permits issued in the year to 22 November 2026:

  • General Office had 495 permits, more than the other 7 types of space combined, and the shortest median, 21 days.
  • Health Care Office permits took a median 31 days, against 21 for an office, and 1 in 10 took longer than 101 days.
  • Restaurant - Class 1 shared Retail Store’s 26-day median, but its slowest tenth went past 99 days, against 74 for retail.
  • Beauty and Wellness Centre had the longest median, 38 days, and the longest slow tail, 120 days, from only 17 permits.
  • Wholesaling - Class A had a 33-day median but the shortest slow tail of the 8, at 60 days.

The chart shows each type’s median, with Health Care Office marked. The table adds the permit count and the slow tail for every row.

How long commercial renovation permits take in Vancouver, by type of business

Data refreshed . Source: City of Vancouver Open Data Portal: Issued building permits.

Median days to a commercial renovation permit, last 12 months, by type of space
General Office: 21 General Office 21 Retail Store: 26 Retail Store 26 Health Care Office: 31 Health Care Office 31 Barber Shop or Beauty Salon: 31 Barber Shop or Beauty Salon 31 Restaurant - Class 1: 26 Restaurant - Class 1 26 Wholesaling - Class A: 33 Wholesaling - Class A 33 Fitness Centre: 32 Fitness Centre 32 Beauty and Wellness Centre: 38 Beauty and Wellness Centre 38
How long commercial renovation permits take in Vancouver, by type of business: the full table
Type of space (City category) Permits issued Median wait (days) 1 in 10 waited longer than (days)
General Office 4952166
Retail Store 1202674
Health Care Office 7531101
Barber Shop or Beauty Salon 223176
Restaurant - Class 1 202699
Wholesaling - Class A 193360
Fitness Centre 183270
Beauty and Wellness Centre 1738120

How we collected it

Permits in the City's PermitCategory 'Renovation - Commercial/ Mixed Use - Lower Complexity' (the City's grouping of higher-volume, lower-complexity commercial alteration permits) first issued in the 12 months before the refresh date, grouped by the City's SpecificUseCategory; records with 'Not Applicable' are left out and the 8 categories with the most permits are shown. Days are the City's PermitElapsedDays: calendar days, weekends and holidays included, from the day the application got a permit number to the day the permit was first issued, so they include time the applicant spent completing the application and answering conditions. Median and 90th percentile are computed by the portal's aggregate functions (percentiles are estimates) and rounded to whole days. Applications still in progress or withdrawn are not in the data. Addresses, applicants and contractors are not used. Contains information licensed under the Open Government Licence - Vancouver (https://opendata.vancouver.ca/pages/licence/).

Period covered
to
Data refreshed
November 22, 2026

Commercial renovation permit times in Vancouver, by type of space

Local data, Commercial renovations

Updated

By the Delwin Construction team

The data: one row per type of space, with its slow tail

Each row is one of the City’s use categories, and the labels are the City’s own, so “Restaurant - Class 1” appears exactly as the City records it. Three columns matter:

  • Permits issued: the count behind the row.
  • Median wait: line the row’s permits up from quickest to slowest, and this is the one in the middle.
  • 1 in 10 waited longer than: the 90th percentile, so 9 in 10 permits came through within it.

Row size changes how far you can lean on a number. General Office rests on 495 permits, while the five smallest rows have 17 to 22 each, so a few slow or quick permits can move them at the next refresh.

The City has published a figure of its own, and it measures something different. City staff presented a July 2024 update that put the median for commercial renovation permits at 32 days, down from 56 in 2022. That figure covers another period and isn’t broken down by type of space, so treat it as a separate measure, not a point on the same trend as these rows.

Methodology: lower-complexity commercial permits, in calendar days

The table rests on four choices, each set out below: the source and filter, the time window and grouping, what the clock counts, and how the statistics are worked out.

Source and filter

The rows come from the City’s Issued building permits dataset, whose current-year extract the City refreshes every day. We keep one City grouping, “Renovation - Commercial/ Mixed Use - Lower Complexity”. The City derives it from three fields, the type of work, the property use and the project description, to pick out common, simpler jobs.

Window and grouping

A permit counts if it was first issued within a year of the refresh date. Each one is filed under its SpecificUseCategory, the City’s label for how the property is used. Records marked “Not Applicable” are dropped, and only the 8 labels with the most permits make the table.

The clock

PermitElapsedDays starts when an application is given its permit number and stops when the permit is first issued, and every calendar day counts, weekends and holidays too. The City’s field note lists what moves it: the queue of applications, whether the application is complete, the site and project requirements, and how fast staff and the customer respond.

The statistics

The portal’s own aggregate functions return the median and the 1-in-10 figure, a 90th percentile the portal estimates, and we round both to whole days. Only totals are used, and nothing on this page identifies an address, an applicant or a contractor. The City publishes the data under the Open Government Licence - Vancouver, and the note under the table carries the attribution it asks for. The filters and the rounding are our choices; no one at the City has checked this page.

What it means for you: match your dates to your type of space

Find the row for your kind of business and read the last column first. If a fixed date depends on the permit, such as when rent starts or when you open, set it from the 1-in-10 figure for your type of space. For a health care office that means 101 days, not the 31-day median.

Some of those days are yours. An application that arrives complete, and prompt replies when the City sets conditions, shorten the part of the wait the applicant controls.

Office tenants may have a quicker route. The City’s Tenant Improvement Program (TIPs) is open to offices in buildings on its TIPs list. That list automatically includes commercial office buildings whose building permit was applied for after January 31, 2007. Its targets are counted in business days. The table can’t show how many of the 495 General Office permits went that way. So don’t read the TIPs targets into the office row, or the office row into TIPs. Before you sign a fit-out contract, see what to check before hiring a contractor in BC.

For the work itself, see commercial renovation in Vancouver. To build the permit wait into a fit-out schedule, book a free on-site consultation. Renovating a home instead? The City of Vancouver building permit wait times for home renovations are on their own page.

Limits of the data: issued permits only, in the City’s own categories

  • Only permits that were issued are counted. An application still under review, or one that was withdrawn, isn’t in any row, and those may be the longest waits.
  • A use category describes the space, not the size, cost or scope of the job.
  • The City’s lower-complexity grouping leaves out bigger or more complex commercial jobs, so they aren’t counted.
  • Permits recorded with more than one use, and kinds of space outside the 8 largest groups, don’t appear in the table.
  • The days can’t separate the City’s review time from the applicant’s.
  • Only the City of Vancouver’s permits are here; Burnaby, Richmond and the rest of Metro Vancouver issue their own.

Last refreshed: quarterly, from the City’s open data

Every quarter we run the same query on the City’s portal for the latest 12 months and rewrite the findings if the rows change order. The Data refreshed line under the table gives the date of the last run.

Questions people ask

How long does a commercial renovation permit take in Vancouver?

It depends on the type of space. Take the City's lower-complexity commercial renovation permits issued in the year to 22 November 2026. Their median ran from 21 days for a General Office to 38 for a Beauty and Wellness Centre. One in 10 permits waited past 60 to 120 days, depending on the space. The count starts at the permit number, so the applicant's replies are in it.

Do clinic renovations take longer than offices?

In the City's data, yes. Its rows have no clinic label, and the nearest is Health Care Office. Those permits came through in a median 31 days in the year to 22 November 2026, against 21 for a General Office. One in 10 took longer than 101 days, against 66 for offices. The data doesn't record why.

Is there a faster path for office tenants?

Possibly, if the office sits in a building on the City's TIPs list. Office buildings whose permit application came after January 31, 2007 are listed automatically. For that stream the City targets 5 to 10 business days for its first review, then issues the permit within 1 to 2 business days of a passed field review. This page's office median doesn't separate TIPs permits, so compare with care.

Start with a free on-site consultation

We visit the space and send a free quote with clear, detailed pricing. Kiera K. wrote about working with us from the initial consultation to the final touches.

Call (604) 808-8567 Book a free on-site consultation