City of Vancouver building permit wait times for home renovations

City of Vancouver building permit wait times for a lower-complexity home renovation vary by type of home: detached houses wait weeks longer than apartments, townhouses and triplexes. In the 12 months to 22 November 2026, the median wait was 13 days for a Multiple Dwelling and 39 for a detached house.

By the Delwin Construction team Updated

Open-concept white shaker kitchen with a quartz island, brass pulls and globe pendant lights

Key findings: detached houses wait weeks longer, suites longest

Renovation permits in the City’s Dwelling Unit and Multiple Dwelling categories have the shortest median waits. Detached houses wait weeks longer, and houses with a secondary suite wait longest. These figures cover permits issued in the 12 months to 22 November 2026:

  • A Multiple Dwelling permit had a median wait of 13 days.
  • A Single Detached House permit had a median wait of 39 days.
  • A Single Detached House w/Sec Suite permit had a median wait of 48 days, the longest of the five types of home.
  • The slowest tenth of Single Detached House permits waited longer than 138 days.

The chart shows the median for each type of home, and the table adds how many permits sit behind each row and the 90th percentile.

How long renovation permits take in Vancouver, by type of home

Data refreshed . Source: City of Vancouver Open Data Portal: Issued building permits.

Median days from permit number to issue, last 12 months, by type of home
Multiple Dwelling: 13 Multiple Dwelling 13 Single Detached House: 39 Single Detached House 39 Single Detached House w/Sec Suite: 48 Single Detached House w/Sec Suite 48 Dwelling Unit: 11 Dwelling Unit 11 Duplex: 21 Duplex 21
How long renovation permits take in Vancouver, by type of home: the full table
Type of home (City category) Permits issued Median wait (days) 1 in 10 waited longer than (days)
Multiple Dwelling 3091380
Single Detached House 26439138
Single Detached House w/Sec Suite 10248155
Dwelling Unit 841161
Duplex 3021101

How we collected it

Permits in the City's PermitCategory 'Renovation - Residential - Lower Complexity' (the City's grouping of higher-volume, lower-complexity residential alteration permits) that were first issued in the 12 months before the refresh date, grouped by the City's SpecificUseCategory; the 5 types of home with the most permits are shown. Days are the City's PermitElapsedDays: calendar days, weekends and holidays included, from the day the application got a permit number to the day the permit was first issued, so they include time the applicant spent completing the application, answering conditions and booking a field review. Median and 90th percentile are computed by the portal's aggregate functions, which estimate percentiles; days are rounded to whole days. Applications still in progress or withdrawn are not in the data. Addresses, applicants and contractors are not used. Contains information licensed under the Open Government Licence - Vancouver (https://opendata.vancouver.ca/pages/licence/).

Period covered
to
Data refreshed
November 22, 2026

City of Vancouver building permit wait times for home renovations

Local data, Permits in Vancouver

Updated

By the Delwin Construction team

The data: the median is the typical wait, not the longest

The median is the middle permit: half were issued faster and half slower. The 90th percentile, in the table’s last column, is the wait only the slowest tenth of permits went past. That slow tail is the figure to plan with. Rows built from fewer permits move more between refreshes, so check the Permits issued column too.

The types of home are the City’s own categories. In its Zoning and Development By-law, a Multiple Dwelling is an apartment, townhouse or triplex, and a Dwelling Unit is “a self-contained housekeeping unit”. A Single Detached House w/Sec Suite holds a main home and a secondary suite.

Methodology: the clock runs from permit number to issue

The rows come from the City of Vancouver’s Issued building permits dataset, which the City updates daily for the current year. We keep permits in the City’s category “Renovation - Residential - Lower Complexity”, which the City describes as higher-volume, lower-complexity project scopes. Each was first issued in the 12 months before the refresh date. We group them by the City’s use category and show the five types of home with the most permits.

Each wait is the City’s PermitElapsedDays: calendar days, weekends and holidays included, from the day an application gets a permit number to the day the permit is first issued. The City’s own published processing times are measured the same way. So the days include the applicant’s time completing the application and answering the City’s conditions. On the field review route for small renovations, the site inspection comes before the permit is issued, so that wait counts too.

The portal estimates the median and the 90th percentile, and we round them to whole days. Only totals are used: no addresses, applicants or contractors. Contains information licensed under the Open Government Licence - Vancouver. The grouping and rounding are ours, and the City has not reviewed this page.

What it means for you: plan around the slow tail, not the median

A start date set from the median would have been late for half of these permits. If a late start would cost you, such as a lease ending, set the date from the 90th percentile for your type of home.

The clock includes the applicant’s time, so a complete application and quick answers to the City’s conditions are the parts you or your contractor control. Our guide to which renovations need a City of Vancouver permit explains what to apply for.

A simple renovation under $250,000, such as a kitchen or bathroom update, may qualify for the City’s Residential Renovation Fast Track; structural changes, additions and adding a secondary suite don’t. The fast track covers only some permits, so its one-week timeline isn’t comparable with the medians here. Don’t apply too early either: a permit becomes void if work doesn’t start within 6 months of the date it was issued.

For a suite, our guide to making a basement suite legal in Vancouver covers the extra permits. For a basement finished as part of the house, see basement renovations in Vancouver. For work across several rooms, see whole-home renovations in Vancouver. To plan a start date with the permit wait built in, book a free on-site consultation.

Limits of the data: it can’t predict your own permit

  • A median describes the middle permit, not yours, and the data can’t separate the City’s time from the applicant’s.
  • Only issued permits count. Applications still in review, or withdrawn, are missing.
  • The type of home says nothing about the size or cost of the work, and permits outside the City’s lower-complexity renovation category are left out.
  • Only the five types of home with the most permits are shown.
  • It covers the City of Vancouver only, not Burnaby, Richmond, North Vancouver or other Metro Vancouver municipalities.

Last refreshed: the City’s figures are re-pulled every quarter

We re-pull the rows from the City’s portal every quarter, which moves the 12-month window forward, and check the key findings on this page against the new rows. The date marked Data refreshed under the table is when the rows were last pulled.

Questions people ask

How long does it take to get a building permit in Vancouver for a renovation?

For a lower-complexity residential renovation, the wait varies by type of home. In the 12 months to 22 November 2026, the median was 13 days for a Multiple Dwelling (an apartment, townhouse or triplex) and 39 days for a Single Detached House. Houses with a secondary suite waited longest. The days run from permit number to issue and include the applicant's own time.

Why do permits for a house with a secondary suite take longer?

The City's data doesn't record why. The City does publish two rules. Adding or legalizing a secondary suite needs a development permit as well as a building permit, and that work can't use the Residential Renovation Fast Track. The data doesn't show how many of these permits were for suite work, so treat those rules as context, not the cause.

Does the permit wait include the time I take to answer the City's conditions?

Yes. The City counts calendar days from the day an application gets a permit number to the day the permit is issued. Time spent completing the application, answering the City's conditions and, on the field review route, waiting for the site inspection all counts. The City lists customer response times among the things that affect its timelines.