Vancouver renovation permits by neighbourhood: waits and counts

Vancouver renovation permits by neighbourhood differ by weeks: the city-wide median wait for a home renovation permit was 35 days, against 77 in Shaughnessy. In the 12 months to 22 November 2026, the City issued 1,056 home renovation permits, and the balance between renovating and rebuilding varied widely by neighbourhood.

By the Delwin Construction team Updated

Open-concept white shaker kitchen with a quartz island, brass pulls and globe pendant lights

Key findings: the same permit can take weeks longer in one neighbourhood than another

In the 12 months to 22 November 2026, the City of Vancouver issued 2,639 home permits: 1,056 for renovations and additions, 969 for new buildings and 614 for demolitions. What stands out for anyone planning work:

  • A renovation permit’s median wait city-wide was 35 days, and 1 in 10 waited longer than 182 days.
  • A new-building permit took nearly five times as long at the median, 170 days. A demolition permit took 108.
  • In the four neighbourhoods with a page in November 2026, the renovation median ran from 44 days in Kitsilano to 77 in Shaughnessy.
  • The slow tail spread even wider. The slowest tenth of renovation permits waited past 265 days in Kensington-Cedar Cottage, but only past 150 in Dunbar-Southlands, sooner than the city’s 182.
  • What owners declare varies more than the wait. The median declared value of a renovation permit was $60,000 city-wide, $42,500 in Dunbar-Southlands and $175,000 in Shaughnessy.

Declared value is the cost estimate an applicant gives the City to set the permit fee, not a price anyone paid. The tables below give the city’s figures by type of work, then each neighbourhood with its own page.

Vancouver home permits: renovations, new buildings and demolitions, last 12 months

Data refreshed . Source: City of Vancouver Open Data Portal: Issued building permits.

Median days from permit number to issue for Vancouver homes, by type of work
Addition / Alteration: 35 Addition / Alteration 35 Demolition / Deconstruction: 108 Demolition / Deconstruction 108 New Building: 170 New Building 170
Vancouver home permits: renovations, new buildings and demolitions, last 12 months: the full table
Type of work (City category) Permits issued Median wait (days) 1 in 10 waited longer than (days)
Addition / Alteration 1,05635182
Demolition / Deconstruction 614108279
New Building 969170404

How we collected it

Building permits the City of Vancouver first issued in the 12 months before the refresh date for residential property (the City's PropertyUse 'Dwelling Uses') anywhere in the city, grouped by the City's TypeofWork: 'Addition / Alteration' (renovations and additions to existing homes, every complexity), 'New Building' and 'Demolition / Deconstruction'; other types of work (temporary buildings, salvage and abatement) are left out. Rows are in alphabetical order, so renovations come first. Days are the City's PermitElapsedDays: calendar days, weekends and holidays included, from the day the application got a permit number to the day the permit was first issued, so they include time the applicant spent completing the application and answering conditions. Median and 90th percentile are computed by the portal's aggregate functions (percentiles are estimates) and rounded to whole days. Applications still in progress or withdrawn are not in the data. Addresses, applicants and contractors are not used. Contains information licensed under the Open Government Licence - Vancouver (https://opendata.vancouver.ca/pages/licence/).

Period covered
to
Data refreshed
November 22, 2026

Vancouver renovation permits by neighbourhood: waits and counts

Local data, Renovating by neighbourhood

Updated

By the Delwin Construction team

City of Vancouver, neighbourhood by neighbourhood

Each neighbourhood below has its own page with the full table and what the numbers mean there. Records is the number of records behind each neighbourhood's figures. A neighbourhood with fewer than 30 records has no page of its own; its records are counted in the City of Vancouver row.

City of Vancouver: every neighbourhood with a page
Neighbourhood Renovation and addition permitsMedian wait for a renovation permit (days)
Dunbar-Southlands 176 records 4247
Kensington-Cedar Cottage 223 records 6848
Kitsilano 158 records 9144
Shaughnessy 85 records 3477
City of Vancouver 2,639 records 1,05635

The data: a neighbourhood gets its own page once its numbers can carry one

The first table splits the city’s home permits by the City’s own type of work. “Addition / Alteration” covers renovations and additions to existing homes of every size and complexity. The second table lists each neighbourhood with a page: its Records column counts all three kinds of home permit there, and the next two columns give its renovation permits and their median wait.

We write a neighbourhood page only when the City issued at least 30 renovation permits there over the 12 months. Below that, a handful of unusual permits can move a median by weeks, and the page would describe chance rather than the neighbourhood. Every local area without a page is still inside the City of Vancouver totals, so if yours isn’t listed, plan with the city row.

Each neighbourhood page adds what a table can’t. It shows whether the area mostly renovates or rebuilds and what owners there declared for their renovations. It also gives the area’s count of Vancouver Heritage Register buildings in the City’s 2023 data. Then it says what those numbers mean for a renovation in that area.

Methodology: one City dataset, three types of work, the City’s local areas

All the permit figures come from the City of Vancouver’s Issued building permits open data. We take permits for residential property (the City’s “Dwelling Uses”) first issued in the 12 months before each refresh. They’re grouped into the City’s three types of work for homes: Addition / Alteration, New Building, and Demolition / Deconstruction. Temporary buildings and salvage and abatement permits are left out.

The neighbourhoods are the City’s own local areas, of which there are 22, and each page uses the City’s name for its area. That is why the page for Dunbar is titled Dunbar-Southlands.

The wait is the City’s PermitElapsedDays field. It counts calendar days, weekends and holidays included, from the date an application is given a permit number to the date the permit is first issued. Because the applicant’s time inside that span is counted too, a wait reflects both sides of the process.

For each type of work in each area, the City’s portal returns a count, a median and an estimated 90th percentile, and we round both waits to whole days. The median is the permit in the middle of the line. The 90th percentile is the wait that only the slowest tenth of permits went past. Our tables hold totals only, with no addresses, applicants or contractors. We chose the 12-month window, the grouping and the 30-permit bar, and the City has not reviewed these pages.

What it means for you: check your neighbourhood’s slow tail before you pick a start date

Start with your neighbourhood’s renovation figures. If a late start would cost you, plan from the “1 in 10 waited longer than” figure rather than the median. A lease that ends or trades already booked are the usual reasons. In Kensington-Cedar Cottage, for example, the median was 48 days but the slowest tenth waited more than 265.

Renovating and rebuilding run on different clocks. City-wide, the median new-building permit took 170 days and the median demolition permit 108, and a teardown and rebuild needs a permit for each. In Dunbar-Southlands the City issued 77 new-building permits against 42 for renovations, so there the rebuild route is the more common one.

A simple update under $250,000, such as a new kitchen or bathroom with no structural work, may fit the City’s Residential Renovation Fast Track. That program issues permits within one week. Our medians mix those permits with additions, structural work and suites, so the two figures don’t measure the same thing. Time your application to your build: a City permit lapses if work hasn’t started within 6 months of its issue date.

For waits by type of home, our page on City of Vancouver building permit wait times splits lower-complexity renovation permits into houses, houses with suites and apartments. Our guide to which renovations need a City of Vancouver permit covers what to apply for. These figures are City of Vancouver permits only: other Metro Vancouver municipalities issue their own permits under their own rules. Planning a whole-home renovation in Vancouver and want the permit wait built into the schedule? Book a free on-site consultation.

Limits of the data: an issued permit’s history, not a forecast for yours

  • Only issued permits count. An application still in review, or one that was withdrawn, isn’t in the data, so an area with many stalled applications can look quicker than it is.
  • A neighbourhood’s figures rest on far fewer permits than the city’s. Shaughnessy’s renovation row holds 34 permits against the city’s 1,056, so its median can shift by weeks from one refresh to the next.
  • The data records how long a permit took, not why. Nothing in it separates the City’s review time from the applicant’s.
  • The type of work says nothing about the size of the job: “Addition / Alteration” covers a bathroom update and a major addition alike. Declared values are the only size signal, and they are estimates made for the permit fee.
  • The neighbourhood rows don’t add up to the city row, because most local areas don’t have a page.

Last refreshed: every neighbourhood moves forward on the same day each quarter

Every quarter we pull the city’s rows and every neighbourhood’s rows from the City’s portal on the same day. The 12-month window moves forward for all of them at once. The declared values on the neighbourhood pages are re-queried that day too. The date marked Data refreshed under the first table is the day of the last pull. If a neighbourhood drops below 30 renovation permits, its page folds back into this one until it recovers.

Questions people ask

Which Vancouver neighbourhood has the longest renovation permit wait?

Among the neighbourhoods with a page in November 2026, Shaughnessy. In the 12 months to 22 November 2026, its median renovation permit took 77 days, more than double the city's 35. For the slowest tenth of permits, Kensington-Cedar Cottage was longest, at more than 265 days. Local areas without a page aren't ranked here.

Why doesn't my neighbourhood have its own page?

Either the City issued fewer than 30 renovation permits there over the 12 months, or its page hasn't been written yet. Below 30, a few unusual permits can swing the median by weeks, so we don't publish one. Your area's permits are still counted in the City of Vancouver row, and that row is the figure to plan with.

Do these permit waits count only the City's review time?

No. The clock runs from the day an application is given a permit number to the day the permit is first issued, weekends and holidays included. That span holds the applicant's own time finishing the application and answering the City's conditions, so a complete package and quick replies can shorten it.

Can I see which permits were issued near me?

Not on this page, which uses totals only and never shows an address. The City of Vancouver's online permit search finds existing permits and applications by address, permit number or date. You can use it to look up your own street before you plan your work.